MAD3 completed the design and documentation of the sewer reticulation and roads and drainage for the crossover, service and entrance laneways. MAD3 engaged with Underground Power Development Pty Ltd as a sub-consultant for the Design and Documentation of the underground power design. A number of contractors completed the Civil Construction works through a selected tender process.
Scope Of Work
- Design and documentation of sewer reticulation, roads and drainage for the crossover
- Sub-consultant engaged for the design and documentation of the underground power design.
Project Challenges
Upon a predesign site inspection, it was determined that a sewer main extension along Butler Boulevard to service the site was possible but would have been a very costly exercise.
How We Managed This
MAD3 liaised closely with Water Corporation and the Developer and ultimately designed and obtained approval to install the sewer within private property. The end result was a cost saving of about $100K to the Developer.
Value Engineering
MAD3 was commissioned to coordinate and provide an overall master plan for the entire site to
ensure that all the levels and layouts within all four lots was achievable and tied in smoothly.