The scope of work included Design and third party certification of temporary works; Lifting studies and installation procedures; Lifting equipment; Steel platforms; Pipe supports; Plant equipment supports and foundations.
project challenges included quick response times; information required from third parties; lack of site-specific geotechnical information requiring conservative assumptions. We overcame these by leveraging on our office location being close to site and dedicated liaison engineer for the project; proactive approach and good communication with Salini Impreglio – NRW JV team; optimised design to meet conservative assumptions.
The real key was the value engineering on the project including timely response of MAD3 dedicated engineer avoided site delays; optimised design of foundations for heavy plant equipment; flexible design approach to include material available on site and contractor’s preferred installation process.