Cranbrook WA Water Treatment Plant Upgrade – Water Utility

Our client required a plant upgrade to provide enhanced treatment of the water source and manage forecasted future demand at the Cranbrook WTP.

Level 4 treatment was required due to pathogen contamination. Equipment included Ultraviolet (UV) disinfection unit and Ultra Filtration (UF) package.

WestWater tendered for execution of this project and engaged MAD3 Engineering (formerly MA Deacon Engineers) to provide engineering services for mechanical and structural concrete engineering, with the detailed design for the site integration.

Scope Of Work

  • General site layout design and mechanical integration
  • Hydraulic design and 4x pump selection review
  • Piping, structural concrete, concrete pads for the tanks, earthwork details for pits, site earthworks set-out, hardstand design, electrical design
  • Technical management of switchboard designer/manufacturer
  • Technical management of solar designer/installer
  • Western Power liaison
  • Electrical site layout and building internals, cable schedules (both power & instrument/control/comms).

Project Challenges

  • Verification/ Validation of Preliminary Design that was performed by others
  • Solar designer provided the information for WestWater to make the regulatory applications
  • HVAC design: Air conditioner unit sizing by supplier engaged by WestWater
  • Drawings prepared in accordance with DS80 and DS81 and delivered to WestWater for them to deliver to end-customer Water Corporation.

How We Managed This

MAD3 have a good understanding of the Water Corporation standards and have completed many engineering and detailed designs (including under D&C contracts) for the Water Corporation.

Value Engineering

  • Existing infrastructure reused
  • Pipe diameters were derived from the Water Corporation Pipeline Selection Guidelines, and in the absence of information and where a variety of inner dimensions were available, the smallest was taken.
Piping arrangement with 3 inline filters.

Type of Work:

Mechanical Engineering, Structural Engineering

Location:

Australia, Cranbrook, Western Australia

Engineering Phase:

Detailed Engineering

Industries:

Infrastructure

Duration:

12 months

Type of
Work:

Mechanical Engineering, Structural Engineering

Location:

Australia, Cranbrook, Western Australia

Engineering
Phase:

Detailed Engineering

Industries:

Infrastructure

Duration:

12 months